MEPs back two-year methane delay: what importers and operators must now measure, and when

Fixed gas monitor

MEPs back two-year methane delay: what importers and operators must now measure, and when

28 Nov, 2026
International Environmental Technology
3 min read

Parliament has endorsed giving fossil fuel importers until 2029 to apply EU-equivalent methane monitoring, and operators two more years for verified measurement reports. One Council vote remains.

The European Parliament voted on Thursday 26 November 2026 to endorse a provisional agreement that postpones key parts of the EU Methane Regulation by two years.

MEPs backed the deal by 341 votes to 224, with 31 abstentions.


Find your next gas detectors or monitors in our international directory.


The agreement amends Regulation (EU) 2024/1787, which entered into force on 4 August 2024. Negotiators from Parliament and the Council reached it on 19 November.

Parliament handled the file under its urgent procedure.

Two years, not one

The postponement is longer than the European Commission asked for. Its 14 October proposal sought a one-year delay, which the Council backed in its own position on 6 November.

Parliament had pushed for three years when it set its position in October. The final compromise lands in the middle.

According to Parliament, importers had warned that they might not be able to secure enough compliant supply while energy markets were strained.

They also pointed to high prices linked to the conflict in the Middle East.

Borys Budka (EPP, Poland), lead MEP for Parliament's Industry, Research and Energy Committee, said when the deal was struck: "We stand by the objectives of the methane regulation, but security of supply comes first."

New deadlines for importers

The Council has said that monitoring, reporting and verification (MRV) obligations for importers of crude oil, natural gas and coal will apply from 1 January 2029 rather than 1 January 2027.

By May 2030, importers will have to show that supply contracts concluded or renewed since 4 August 2024 cover only fuel subject to MRV measures equivalent to the EU's.

The same date applies to their reports on efforts to bring older contracts into line.

Methane-intensity reporting, for both importers and EU producers, moves from 5 August 2028 to 5 August 2030.

New deadlines for EU oil and gas operators

The delay is not confined to imports. EU oil and gas operators also gain two years to submit verified reports that combine source-level and site-level methane measurements.

For operated assets, the deadline moves from 5 February 2027 to 5 February 2029.

For non-operated assets, it moves from 5 August 2028 to 5 August 2030.

Same measurement duties, more time

The amendment changes deadlines, not the measurement duties themselves.

Operators still have to reconcile bottom-up, source-level estimates with top-down, site-level measurements, and have the result verified.

The extra time eases scheduling pressure on survey campaigns and verification work, but the technical bar is unchanged.

For importers, the harder problem was never the measurement itself but the evidence chain behind it.

They must show that a producer in another jurisdiction measures, reports and verifies to a standard the EU will accept as equivalent.

Two more years buys time for that evidence to be built, contract by contract.

A review before the new start date

The agreement also sets a check-point. The Commission must review how the regulation is being applied and report to Parliament and the Council by 1 January 2028, then every five years.

Where it judges one necessary, the Commission must also bring forward a legislative proposal.

That review falls a year before importer MRV obligations apply. It leaves room for a further change if equivalence routes are still not in place.

Council vote due in December

The Council must now formally adopt the amendment. A provisional list of Council business for the Environment Council meeting on 11 December 2026 includes adoption of the legislative act.

Items on a provisional list are not confirmed until the final list is published.

Once adopted, the text will be published in the Official Journal. The Council has said it intends the amendment to enter into force before the end of the year.

Until it does, the original 1 January 2027 start date for importer obligations remains in law.

Latest News

PIN 27.5 Oct/Nov 26

Explore our Digital Edition

Discover the latest news and research

Digital edition

Explore Our Other Sites

Labmate Online
Rebuilt London blood group referral lab prepares for DNA-based testing
Explore more Arrow
Envirotech Online
SCA COLUMN: Behind the Blue Book
Explore more Arrow
Pollution Solutions Online
Pump and mixer service at paper mill set to reach 40 years
Explore more Arrow
Chromatography Today
Thermo-analytical GC-MS standard for microplastics in drinking water reaches final draft stage
Explore more Arrow